Powering Tower Cranes with Battery Storage
Tower cranes are the highest peak-load event on any construction site. Here is how battery storage systems absorb crane lift peaks, reduce generator sizing, and eliminate load-related voltage problems.
The Tower Crane Power Challenge
A modern tower crane running a rated lift draws 3 to 5 times its nominal steady-state load during the acceleration phase. A crane rated at 55 kW average may pull 150–200 kW for 3–8 seconds during each lift cycle. If that crane is fed directly from a generator, the generator must be sized to handle the instantaneous peak — meaning the generator is massively oversized for all other moments of operation.
What Happens Without Peak Shaving
Sites without crane-specific power management typically experience one or more of the following problems: generators running at 15–25% average load (wasting fuel), voltage dips during lift events that cause other equipment to fault, or cranes limited to reduced hoist speeds to stay within generator capacity. In worst cases, site managers order a second, larger generator to handle crane peaks, paying for capacity they rarely use.
How Battery Storage Solves This
A BESS unit connected between the generator and the crane handles instantaneous lift current from the battery, not the generator. The generator sees a smooth, averaged load — typically 70–80% of its rated output — and the battery top-up happens between lift cycles when crane load drops to near zero. The result is a generator 30–40% smaller than the peak-only specification, running at peak efficiency, with stable voltage across the entire site.
Sizing for Crane Applications
BuildingFab's application team reviews crane model, rated lift capacity, hoist speed, and anticipated cycle frequency when sizing a BESS for crane applications. The BESS must have sufficient peak discharge current to cover the acceleration phase, and sufficient capacity to support multiple consecutive lifts before generator recharge is needed. Most single-crane sites are served well by the GRES cabinet system. Multi-crane sites typically require the BRES containerized platform.
- Single tower crane: GRES cabinet system typically sufficient
- Multi-crane site: BRES containerized system recommended
- Key spec: peak discharge current must cover crane acceleration phase
- Battery capacity: sized for 2–4 consecutive lift cycles without generator input
Voltage Quality on Crane-Heavy Sites
Beyond fuel savings, crane-adjacent BESS deployment has a notable secondary effect: voltage stability across the site improves significantly. Sensitive equipment — computers, PLCs, LED lighting — on the same distribution circuit as an unhybridized crane feed frequently experiences voltage dip events during lifts. A BESS between the generator and the site distribution eliminates these events, reducing nuisance faults and equipment resets.
More Articles
What Is Hybrid Construction Power?
A practical guide to how battery energy storage systems work alongside generators on modern construction sites — and why the industry is moving away from diesel-only power.
Generator vs Generator + BESS: The Complete Comparison
A detailed look at the real cost and operational differences between running a diesel generator alone versus a hybrid generator and battery system on a construction project.
Get Started
Apply this to your project
BuildingFab's team can assess your site requirements and recommend the right hybrid power configuration.